Perkins Street Housing Development
- Completion Date01 July 2024
Project Description
Cloncurry Shire Council is sub-dividing land on Perkin Street to create 9 new ‘country-style executive homes’ to help improve liveability options to promote economic development. This project will deliver nine new houses in Cloncurry, to attract and retain new families to the town. The project will be delivered in two stages, Stage 1 will be civils/earthworks and Stage 2 will be construction of housing.
Key Features
- 9 country style executive homes
- 6 houses will have 4 bedrooms, and 3 will have 3 bedrooms
Project Status
This project is now complete.
Progress Updates
July 2024
Stage 2, construction of the houses, is now complete.
March 2024
Roofing, plumbing and electrical works are being carried out on the houses.
October 2023
Continuation of housing construction. Steel framing and roof trusses are going up.
March 2023
Civil works associated with the subdivision of the blocks into 9 residential parcels, Stage 1, has been completed. Stage 2, design of the 9 houses, is in progress.
June 2022
Stage 1 works begin.
Funding Source
This project is funded by Cloncurry Shire Council and the Australian Government Building Better Regions Fund (Round 5).
Location
The sub-division is on a block of land, on the corner of Perkins Street and Railway Street.

Senator Anthony Chisholm and Mayor Greg Campbell officially open the Perkins Street Housing Development